Parking an order prevents any shop floor reporting on the entire order. We need to process an order up to a point before parking it. 

Example, order is currently at op 10. Ops 10, 20 and 30 need to be processed, but we want to prevent op 40 from being processed.

 Is there any functionality to prevent a shop order from processing at a specific operation? 

 

Thanks

 

 

 

 

I'm not aware of any way to strictly prevent operation 40 from being reported in such scenario. But you can add an ongoing interruption clocking to operation 40 manually and enter an interruption case / note that clearly indicates to the operator that the operation should not be processed until that cause has been resolved.

Interruption clockings can be added from Shop Floor page or Shop Floor Workbench/Clockings.