In shop order operations, it seems that the Overlap functionality does not work correctly.
While CBS and APB are not used, and Infinite scheduling is used, see the below example,
Calendar configuration has 5 working days (Mon-Fri) 8 AM to 12 PM and 1PM to 5 PM (8 hour day).
Work center utilization - 100 %, all operations efficiency - 100%, Resource capacity of the WC - 100
Operation 10 has 24 Machine Run Time (unit - Hours) and no set up time
Operation 15 has 12 Machine Run Time (unit - Hours) and no set up time and have a Overlap of 50 percent
Same work center for both operation.
As I understand, the start date/time of the second operation should be 12 hours (50% of 24 hours) after starting of the first operation, which should be 1/25/2021 1.00 PM. But it is scheduled as 1/26/2021 10.00 AM (18 hours after).
Is system check something other ? Or system calculate in a different manner ?
Thank you in Advance.
Thushitha