Hello,
I need help to correctly set the deadlines in subcontracting, I was in V9 we had this problem and I do not see any improvement on the 23r1.
I created an external load item and attached a calendar to it, telling it 1 day = 60mm so that I could talk in days but not in hours for subcontracting. I don't know if there's a simpler way of setting this up.
The problem with what I'm doing is that when the subcontracting operation is in progress, if I recalibrate my production order, it doesn't recalibrate the external operation dates correctly.
Translated with DeepL.com (free version)
as long as the external operation is in Released status, the recalibration takes the 10-day delay into account
Remaining Machine Time is set to 10
I advanced my production order from 01/31/2025 to 01/15/2025 and the external operation kept an identical start and end date, but did not take my 10 days into account because the Remaining Machine Time field was set to 0.
i have to make a spe for the subcontracting flow to work correctly i have to miss a setting it's not possible