Hi,
I don't fully understand the date logic in the time-phased supply proposals created by IFS for an end-item (in an engineer-to-order setting).
Can you outline the key types of dates (or 'offsetting inputs') that figure within scheduling. From specifying when the user desires said item, to all the subsequent dates that are generated after BoM explosion. The 'tools' at are disposal are IFS Apps 10, namely, MRP that executes 'Infinite Scheduler' and 'APB' (our method to CBS schedule items to reflect 'live' capacity constraints such as the current load at a given work centre). I'll provide a brief description of our current practice and raise questions alongside that. If there's any misuse, do say so.
Overview:
A 'Required Date' is specified when demand is created, used to say when project 'X' is desired. Does this input need to be constrained by a lead time, whether plausible or not? For instance, can you specify the Required Date for X as 1/1/15? I'm not asking whether the system has an internal lock denying the user the ability to state that value. Instead, would the Need Dates found in the supply elements (production orders) of X be in the past as a result? As, perhaps, the lead time calculation begins in the past with reference to the Required Date stated for the top-level. If so, is the prospect of Need Dates falling into the past a problem? If Need Dates for the works orders/pieces do not occur in the past during this stage of a project's cycle, what causes the Need Dates to be assigned too strictly resulting in an order not finishing before? Is it the basic (pre CBS) lead time associated with X? The underlying assumption in these questions is a causal relationship between Required Date and Need for the top and subsequent levels. Is that correct?
The questions above are skewed towards suggesting the Need Dates for all levels of a project need to be in the future and achievable. I say this because when they are in the past this causes a 'change in priority rule'. For example, if the Need Date for order O is in the past , yet remains in process, the 'Due Date' for that order (equivalent to when its requires by the next level i.e. parent part) is redefined by when the last OP of that order is scheduled to finish + transport time to be booked into stock. This is wholly divorced from the Need Date instead about actual capacity (since APB figures here).
In any case, MRP's main offsetting process raises all the supply orders for a project with their dates (including Need). Let us describe this as a 'rough cut' plan. With these orders sat at 'Planned' status I load them into APB and proceed to use that to bring any orders forwards if there's available capacity (more details on the APB parameters can be provided).
My scheduling problems are fairly simple despite the convoluted line of questioning above. Using the tools on hand, how can I ensure a product has its levels aligned correctly and then scheduled to finish asap. And then multiply this in the context of an MPS that accepts new project at intervals.
Any help would be incredible. Especially insight to how Need Dates behave (and their prescribed used in IFS).
Many Thanks,
Jay