Question

MS Level 1 Supply not being consumed

  • 30 September 2022
  • 2 replies
  • 144 views

Userlevel 5
Badge +9

Hi. we are using Apps 10. We are using MS level 1 set at Make-to-stock and have input our desired forecast, run MS and MRP for components which has generated all the required requisitions perfectly.

 

we have then loaded and released a customer order for the MS part but when we run site MRP it does not consume any of the MS forecasted supply and generates additional requisitions by MRP creating unconsumed supply.

 

What can be causing this to happen?

regards

Jamie 


2 replies

Badge +2

Hi Jamie! Did you run the master schedule job and then run MRP or just ran MRP only?

 

Badge +1

Hello,

you must see this : https://community.ifs.com/buying-procurement-demand-planner-asc-srm-41/ms-level-1-consume-ms-supply-8339

I hope it’s work for you.

tell me if it’s work..

Reply