Hi all, need your ideas on this.
Following is an actual scenario faced by a customer.
· There is a manufactured product (FG) where a forecast is entered in MS Level 1. There is a monthly forecast for this product.
customer order for this product is connected with a project (each CO has it’s own project) Project PNG is used to plan materials for each project.
· Question is how to consume the forecast by Customer Orders ?
· Because once the CO is connected with a project It’s no longer considered for actual demand in MS Level 1 where Project PNG is ‘*’. (Where the forecast is entered). It’s only considered if MS Level 1 record is created with the specific Project PNG.