Hi guys,
In ‘Shop Order Requisitions’, there are two columns called ‘Original Due’ and ‘Planned Due’. This determine the ‘Need Dates’ for the works orders that are raised by accepting the requisitions in question. In turn, dictating to APB (our CBS engine) what to prioritize when a trade-off is required given resource limitations.
How can those dates be changed? Namely, for SST items under planning method B/C. For demand released by a customer or projects that would involve editing the required date, performing MRP and alignment via MRP Action Proposals.
How can we change the Orig. and PLD Due dates for SST items so they are called for now.
thanks,
jay