Hi, can anyone suggest why MRP is picking up demand but not demanding any supply on the below part. Both Structure and routing are at buildable yet i am getting an action message ‘Not Buildable’ but cant understand why?
regards
Jaime
Hi, can anyone suggest why MRP is picking up demand but not demanding any supply on the below part. Both Structure and routing are at buildable yet i am getting an action message ‘Not Buildable’ but cant understand why?
regards
Jaime
Guess the Supply needs to be started before the part and routing revision is phased in since revision is phased in December 1st. Demand is December 6th and you have 17 days lead time