Has anyone managed to insert a fixed schedule delay between the completion of a component part shop order and the start of the parent part shop order where it is consumed?
My scenario is that I want to ensure that the component part shop orders are completed ahead of when they are being demanded. I don’t want them planned to complete one day before the parent part shop order starts. In effect, I want to build slack into the manufacturing schedule created by MRP.
I thought of making the component routing have a longer machine time than I need to build it, which might work but it wouldn’t be obvious looking at the dates. But I’d be interested if anyone else has tried to do this and been successful.
Thanks!