Manufacturing visualizer is used to schedule shop order operations using drag and drop. Operations are typically rescheduled without compression, leaving subsequent operations and shop order finish dates the same. As soon as an operator reports any complete or scrapped quantities, the shop order is again backwards scheduled and the operation start and finish dates revert back. Is this preventable? Can IFS maintain the rescheduled/uncompressed finish date on the scheduled operation?
IFSAPP10
Thanks,
Eric