Hello all, 

I am hoping to understanding if the following functionality is possible in IFS Apps 10 UPD 15. Currently, I have a Lot/Batch tracked part where we define a Lot number upon receipt. Currently, the part is set to backflush. I know that if I change the consumption method (issuing), I can force the system to prompt for a Lot Number. Is the same possible for Backflushing? Ideally, when the user is reporting a Shop Order completed qty in SFWB, the system would prompt them to enter the Lot Number of the component part they are consuming. I have not seen anything in the help that would indicate if this is possible. Any guidance would be greatly appreciated. 

Best answer by Björn Hultgren

You can try below configuration:

  • Set the Reserve/Issue Method to Backflush for the component. Also make sure it is connected to the operation.
    • This will make sure the component is not automatically reserved, and hence, no specific lot/batch number is allocated
  • The operator can now use the Issue Operation Material Manually. In this dialog the user can enter the quantity consumed from each lot/batch number.

 

 

  • since the component part is lot/batch tracked (and assumed the manufactured parent part is also lot/batch tracked and set to multilevel tracked), an error would be given like below if the operator tries to report the operation quantity before having issued the material. 

     

2 replies

Björn Hultgren
Hero (Employee)
Forum|alt.badge.img+25
  • Hero (Employee)
  • 1061 replies
  • Answer
  • August 7, 2023

You can try below configuration:

  • Set the Reserve/Issue Method to Backflush for the component. Also make sure it is connected to the operation.
    • This will make sure the component is not automatically reserved, and hence, no specific lot/batch number is allocated
  • The operator can now use the Issue Operation Material Manually. In this dialog the user can enter the quantity consumed from each lot/batch number.

 

 

  • since the component part is lot/batch tracked (and assumed the manufactured parent part is also lot/batch tracked and set to multilevel tracked), an error would be given like below if the operator tries to report the operation quantity before having issued the material. 

     


Forum|alt.badge.img+17
  • Author
  • Superhero (Customer)
  • 232 replies
  • August 7, 2023

@Björn Hultgren Thank you!