Question

Labour per Hour per Production Line

  • 21 November 2022
  • 3 replies
  • 64 views

Userlevel 1
Badge +4
  • Sidekick (Customer)
  • 6 replies

Hi,

 

Once we have scheduled the work centres we would also like to be able to say the labour required per production line/workcentre based on the routing crew count.  Is there a way to get a summary overview from APB/IFS that shows this type of detail?

 

Thanks 


3 replies

Userlevel 6
Badge +20

For Remaining Man Hours, look in Capacity Requirements Planning on the pages Operations per Work Center (EE), CRP and Shop Order Operations (Aurena/Cloud), and Labor Load Details.

You could also use Shop Order Operations.

Userlevel 7
Badge +23

In addition to the pages/windows mentioned by Matt yo can also use the Visual Planning (IFS Cloud) / Visualizer (IEE) to view labor load graphically

 

Userlevel 1
Badge +4

Thanks for the replies.  We are in the process of moving to the cloud so looking forward to the improved functionality. 

In the short term we will probably go down the shop order operations route

 

Cheers

Reply