Solved

'Include sublevel' tick is automatically checked eventhough automatic disassembly is selected level wise in MRO interim order structure

  • 23 September 2021
  • 1 reply
  • 43 views

Userlevel 4
Badge +9

Hi,

 

MRO customers have highlighted a situation in MRO interim order structure; when you try to perform automatic disassembly level by level via the tree navigator the ‘include sublevel’ checkbox is automatically checked. You can obviously uncheck this prior to performing the disassembly, however the customers’ argument is that when you want to perform disassembly level by level this checkbox shouldn’t be automatically checked, unlike when you’re trying to perform the disassembly via the RMB option in the header.

 

Will this functionality be changed?

icon

Best answer by Devni Panduwawala 23 September 2021, 05:49

View original

This topic has been closed for comments

1 reply

Userlevel 5
Badge +8

Hi Ravindu,

 

This issue is solved via patch 158737 which is available from UPD12 onwards.
 

Best regards,

Devni