Hi all,

We are running a production with a considerably amount of programming (cad/cam/dtp) between operations. We need to register the time used. For that we have created a the work center, Programming. The routing can look like this:

This leaves us with some challenges. The main one is that programming can finish before and after the other operations. E.g. operation 20 can finish before operation 10 (not possible in IFS) and the other way around.

We suspect that we should do this in another way. Any suggestions? 

So both operation 10 and 20 can be done in parallel, but needs to performed before operation 30 can start? I would simply put operation 20 as parallel to operation 10.


My bad, it is of course only the last operation that that cannot be approved. thx