Why is there a gap between the start date of a parent DOP Order and the finish date of its component DOP Order?
24.1.1
Site Mfg. Calendar = 24/7 with all dates generated through 2030.
Site Picking LT = 0.
Each Work Center uses calendar 24/7 (1440 minutes/day) with capacity calculated through 2/15/2025.
Each Work Center has only one resource, valid from 1/1/2020.
All QPAs in every structure = 1.
All lead times have been calculated (manufacturing, purchasing, cumulative).
DOP Header is for 10,000 lb and is the only source of load for these work centers.
DOP Structure has been created but not released.
Each part consists of only one operation in a part-specific work center running at 1000 units/hour, so each level takes 10 hours.
CRP has been performed.
DOP Structure, all levels shown are manufactured parts.
DOP Gantt Chart
DOP Order details
CRP Load showing gaps
I was expecting the four DOP Orders to be slotted for one day each from 8/29 back to 8/26.