Dear all,

The Finish Date of Shop Orders are being changed by the user PPCSGP (that only have access to Shop Floor Workbench).
At the exactly same time the Shop Floor Employee registers the operation and makes a workcenter change the Finish Date is changed by this user (only in some cases).
There are no events created by us that can make this change.
What could be causing this? Before, this did not happen.


Best regards,
Luisa Quintas

Hi @TSCLMQUINTAS ,

The shop order will be automatically rescheduled when the shop order operations are modified such as changing the setup or run time or work center of the operation. Based on the schedule direction of the shop order, finish date will be updated if schedule direction is forward and start date is updated if the schedule direction is backward as per the new schedule.

So, in your example when the work center is changed the operation is getting re-scheduled as per availability and capacity of the new work center which subsequently re-schedule the preceding (if not reported) and succeeding operation and later update the shop order finish date accordingly  which is the date on which the last operation is planned to finish.

HopHe this helps!!

Regards,

Mithun K V  


Hi @EqeMithuV ,

Thank you for your help!
Can you explain how this rescheduling is done? How does the system calculate the new Finish Date based on the Work Center?

Best regards,
Luísa Quintas