IFS Cloud:
When in HR Schedule there is any change on the availability of the employee belonging to a specific labor class (and the Employee has the check box “Use HR Schedule” enabled”, we can clearly see on the Visual CRP, the result of what has been done in HR Schedule (the availability for that specific labor class is reduced by one day if we have defined a day of vacation for the employee in the HR Schedule), but the work center that is allocated to the operation that cannot be performed by that employee is still loaded. What to do in such case? How to align the work center workload in case when we have only that employee who can perform that job? Is it possible to manually reduce the capacity of the work center? Seems not….seems that the only way is represented by the creation of a calendar and a schedule per each one of the different work centers.
Is there anyone who could give me some hint? :)
Thx a lot in advance
Best answer by Björn Hultgren
View original