Hi,
In our DOP structure, shop orders for the same parts will arise on different levels, with different need dates. IFS creates all these seperately.
Is there a setting which tells IFS to create the Shop orders once, at the earliest due date with a lot size that can cover the needs for the complete DOP? A bit like MRP planning method G.
Thanks!