Hi,
We are testing DDMRP and think this planning model is useful for us in a Make To Stock scenario for automotive type customers.
Automotive customers send us a delivery schedule for ~6 months of demand. When I try the DDMRP it creates only one requistion to fill up stock to the top of green level. I would like it to continue to create requistions for the complete 6 months horizon . The reason is that we plan the capacity load based on requisitions and that we want the demand from the top level part to show on the lower BOM-levels.(We would only “firm” the first requisition in a planning)
Is there a parameter that I am missing, or is DDMRP designed for “short term planning”?
Sorry for the swedish screen dump, but it shows that only one requistion is created. Then the stock goes negative 2021-07-13 without any new requistion created by the DDMRP.