Standard - as you say, that is the cost of the manufacturing structure at the start
Estimated - the cost of the shop order at the point it is released after any adjustments have been made to the material and/or operation
Actual - the accumulated cost of the operations completed and the material issued
For a repair shop order, are you using a different part number to perform the repair against?
You can’t use the same part number as the completed product for a repair, because it will definitely not represent the correct cost. A repair shop order should start with no material and maybe one standard operation at the start and then the shop order material and operations should be adjusted first BEFORE releasing the order at which point the estimate will be saved as a snapshot.
Hi
The IFS cost calculation in Part Cost works with manufacturing structures, there you cannot select repair Structure Alternates and set the Standard Cost using Copy Costs to Cost Set 1..
That means the Standard Cost we set by Copying Costs to Cost Set 1 is set for Manufacturing.
So in the Shop Order Costs, what you see as the Standard Cost is the Cost for Manufacturing and we do not have a Standard Cost for Repair.
The Shop Order estimate Cost shows the Cost that will be incurred based on the Shop Order Materials and Operations.
As an example if you create a Shop order and remove all materials and operations, then you would see the Standard Cost in Cost Set 1 for the part as the Standard Cost and the Estimate Cost =0.
This Estimated Cost is calculated based on the information in the Material and Operation Tabs.
The repair material also needed to be issued to this shop order as a component and the cost of that also taking in to account, however if this repair material is owned by the Customer, then the cost of the repair item will be considered as 0.
The Actual Cost also is the Cost based on the Transactions (Material, Operation, General Overhead) taken place against the Shop Order.
During repair, what ever the additional cost incurred for the repair other than the cost of the repair Item is finally posted as SOREP Posting when the Shop Order is closed, that usually captures the cost incurred for the repair using a particular Shop Order excluding the cost of the Repair Item.