I have a Control plans that are not active however there are items that are going into QA and requiring inspections. Is there anything else that can cause an item to go into QA upon being received? 

icon

Best answer by Peter Lundgren 22 April 2022, 00:01

View original

1 reply

Userlevel 4
Badge +7

The selected Receive Case in the Supplier for Purchase Part page will control this, regardless if there is an Active control plan purchasing or not.

 