Can I use C90 (Cost Source) to drive Work center cost to different GL Accounts?
What I did,
Created a Cost Source
Connect the Cost Source to Work Center at Cost Details Basic Data
Created posting control M41 and connect it with Control Type C90
At Posting Control Detail connect Cost Source to an Account.
What I expect;
Once I report machine time, I expect the cost goes to the relevant GL Account based on the above mapping using Cost Source and WorkCentre.
Am I doing the correct thing? Is C90 meant to be use like above? If not how can I use C90?
Page 1 / 1
Hi @AanHGTS ,
Couple of things to note here.
This setup has NOT designed to work on parts where Inventory Valuation = Standard Cost and Cost Level = Cost Per Part
If your part does not fall in to above category then you can check the below
These are all I could think of now. I suggest you to start from these. If the issue persists please let us know.
Thanks, @Tharindu Illangasinghe.
I was trying with the Standard Cost and Cost Level = Cost Per Part.
May I know why it is not designed to work with Standard Cost and Cost Level = Cost Per Part?
Hi @AanHGTS ,
I believe the Cost Source setup is for Actual Costing. Standard Cost Per Part setup does not take the actual costs, instead takes the Part Cost values from Cost Set 1. Therefore, it does not fetch cost sources.