Is it possible to assign multiple resources to a shop order operation?
Example: A Shop order operation is routed to Work Center “X”.
Work Center X is made up of machine resources X01, X02, X03, X04.
A small order will run on X01 only while a large order will utilize all 4 machines. Can X01,X02,X03, and X04 all be assigned to one shop order operation?
An attempt was made to manage it with multiple work centers where X1 represents 1 machine, and X4 represents all 4 machines, but this skews capacity views when a resource is assigned to multiple work centers.