Hi, it seems APB (Advanced Planning Board)has quite a few limitations, particularly around handling work centers with multiple resources. For example, scheduling a workcenter with 8 resources, how do you get the system to divide up the work and time it will take (perhaps 1/8 the time as a single resource)? Workarounds that have been floated include manually splitting up order lines as they come in (not scaleable) and fudging the efficiency factor to say, 800% in this example, also not great. Any other ideas that people have tried? If APB is not capable, have others used any third party scheduling software? Any recommendations?
Thanks
Best answer by Björn Hultgren