What is the trigger for the application defined events ‘NOTIFY_UNCONFIRMED_DAYS and NOTIFY_UNAUTHORIZED_DAYS?
i.e. when you create an event action from these to email the supervisor, at what point should the event be firing?
What is the trigger for the application defined events ‘NOTIFY_UNCONFIRMED_DAYS and NOTIFY_UNAUTHORIZED_DAYS?
i.e. when you create an event action from these to email the supervisor, at what point should the event be firing?
Hi,
Since this is an event that should “trigger” when nothing happens…. You must schedule the connected database tasks for this.
Thanks
We have reported quite a few cases for this for my customers. One case: “THis event only triggers on not authorized days that are confirmed.
It must also trigger on days that are not confirmed since confirmation is NOT mandatory.”
We got a correction on this in solution 284331patch 155385.
This is included in update 10 though - what update are you on?