Hi @Irene Røn,
This issue is fixed from UPD14 patch ID: 160745 (severity 3)
From the fix, the account date is set to a mandatory field, and if it's not set, the commands Save and Save and Report Again will be disabled.
The workaround mentioned in the patch is to manually set the account date before saving.
Hope this helps.
Kind regards,
Dinushi
So, still the Account date is blank - you have to manually select date?
If that is the patch - it is very inconvenient for users booking more than one project on same day, need to add account date for every posting.
Before update 13 the account date was kept from register in/out time, not blanked when choosing “Save and report again” - very helpful!
Hi @Irene Røn ,
Yes I agree that the workaround is inconvenient for users given the scenario. According to RnD’s comments, clearing of the values in the field once you “Save and Report Again” is the expected behavior because the expectation would be to report to a different project, report code etc. with a different time period. Therefore RnD’s solution was to force the user to add the date manually by making it a mandatory field.
Hope this helps.
Kind regards,
Dinushi
Hi @Irene Røn,
This issue is fixed from UPD14 patch ID: 160745 (severity 3)
From the fix, the account date is set to a mandatory field, and if it's not set, the commands Save and Save and Report Again will be disabled.
The workaround mentioned in the patch is to manually set the account date before saving.
Hope this helps.
Kind regards,
Dinushi
Hello,
Glad if you could mark this as the best answer if it answered your question.
Thanks!
Kind regards,
Dinushi
The account date was made a mandatory field from UPD14 sev 3 patch ID 160745.
Additionally, the code fix from UPD15 sev 2 patch ID 161949 re-sets the account date without keeping it empty. This patch also resolves the issue of Project Activity LOV data not loading.
Applying these two patches will resolve the issue you are facing.
Kind regards,