All,
It looks like an Resource has a capacity of 8,5 hours in the Resource Analysis window, but it should be in fact 8 hours.
The employee is set with the following schedule, so 8 hours of work between 8:30 and 17:00 o’clock
With this setup I expect 8 hours per day as the capacity, but in the resource analysis windw it shows 8,5 hours:
Do I miss anything, or is this not correct in IFS (IFS Cloud)?
Thanks in advance,
Robert Kool