Hello experts,
I have some wage codes that are of type “lost time” due to mandatory resting, shuttling and similar. These codes needs to be costed by project and is part of scheduled time.
When we need to calculate actual worked time, these wage codes needs to be excluded. Instead of excluding specific wage codes in each calculation, I have simply setup these as absence wage codes.
I am able to register the codes - 8 hours in project and 8 hours as absence. Scheduled time is 8 hours. However, when I try to authorize, system says that my hours do not reconcile. I have used parameter list “Reconcile Job and Attendance Hours”.
As far as I understand from previous discussion, it is possible to use absence in project hours. Any ideas of what can be wrong?
Thank you for your help!