Hi,

 

We have quite recently started with IFS and i am working with projects and tasks.

We use tasks to report project time on however we struggle a bit if for example the designer can start a few days earlier than what we agreed on, and want to register time ahead of the activity start. 

Can you somehow use the offset function but with a negative number? So we do not need to change the activity early start and change the Gantt schedule?

 

Appreciate all the help i can get.

/John

Hi John,

 

Suggesting you to create this post in section - Products (Manufacturing, Products, Engineering, WaDaCo)

https://community.ifs.com/products-manufacturing-products-engineering-wadaco-40 <img class=" src="https://d3odp2r1osuwn0.cloudfront.net/2021-05-18-36833e0f/dist/emojione/263a.png" />

 

Thanks and Best Regards

Madusha


Hi @john.eriksson ,

As per my understanding,  you are not able to use the offset function with a negative number in the standard IFS application. However, you may check the possibility to achieve this via IFS Consultancy through a customization.

Best Regards,
Thanushi