In IFS Aurena - when I report Balance Withdrawal a button called “Generate Normal Hours for Job Hours” turns up. What is the purpose with this button? 

 

BR

Karolina

Hi Karolina,

 

Can you please explain how you report ‘Balance Withdrawal’?

 

Best Regards,

Shehan Almeida.


Hi Shehan,

 

Please see attached document describing how I report Balance Withdrawal.

 

Best regards,

Karolina


Hi Karolina,

 

Thank you. It re-creates. I haven't figure out the impact of this.I will further investigate and let you know.

 

Thank you,

Shehan Almeida.


Hi Shehan,

 

Thank you! It would be very good to know the purpose of this button when using project reporting. 

I got this tip from a colleague - “This is basically to fill the hours in T&A area for the employees who report hours on Shop orders, work orders etc; as when you report time on them the respective hours would not be inserted in the T&A area, until you confirm the record.

 

I did some more test when using project reporting and could not find any use of this button when using project reporting. I attach a document showing my tests. Maybe the button should not be shown when using project reporting? 

I am looking forward to hear from you.

 

Thank you,

Karolina


Hi Karolina,

 

I have reported this to RnD since it seems like a core functionality or an issue.

I will get back to you once I hear from them.

 