Skip to main content

Hello,

We have setup Calendars and Schedule Exceptions in IFS Cloud. When we look at the PSO Gantt, the schedule exceptions related to the Calendars are not reflected for the resources.

We see Calendars are mapped with Scheduling Datasets. But when we send a Full Load, we do not see the Calendar information passed to PSO.

Are calendars from Cloud not sent to PSO? If yes, do we have alternatives to handle calendar exceptions in PSO apart from using Miscellaneous Resource Allocations? Please let me know.

Kind Regards

Priyanka Cecilia

Be the first to reply!

Reply