Hi Community,
We are using Apps 9 Update 15. It has been discovered that there is an issue with Work Orders, specifically the No Part Requisition Lines.
The scenario is that, after we created and saved the requisition header. When we add Requisition Lines, and after adding all the required information, and saving, the Quantity is removed from the line. This results in a loop whereby we cannot continue.
Surprisingly, if we look at the Purchase Requisition outside of the Work Order, all of the information is present and allows for the conversion to a Purchase Order. We are using Work Orders for CAPEX Orders, and we are unsure if finalising the requisition outside of the WO will cause any posting control issues, or facilitate the Financial Project processing.
Any thoughts and suggestions will be appreciated.
Regards
Ken