Im facing an issue now with PO stgaes (on PO lines) where they receive and the Approval both are showing on the sub project navigator.

 

i was trying to exclude the project in the receiving porsing (M197) but the system doesnt allow me to chnage this setting:

At the end it sors itself out but befor the last stage is handled its sitting both in the navigator and connected to the project..

 

were it gives a drop menu...so it looks like its changeble..

 

anyone has  a sollution or experience with this one?

 

 

@Rschuil Check if Project pre-posting (AC2) is used for posting M197 in the Posting Control? If you dont want this to be appeared in the Project side, you can remove it. I hope I got your requirement correct.


how can i check this? 

 


@Rschuil I didnt notice the Project pre-posting set to Include Project Pre Posting for APPRINVSP. In that case, preposting is included by default and it cannot be changed as it is hard-coded.