Question

Open Requisition Linked to Cancelled Purchase Order

  • 2 December 2022
  • 2 replies
  • 154 views

Userlevel 4
Badge +11

Is it possible to reopen a Requisition linked to a Cancelled PO?

 

A User cancelled a Purchase Order, but did not select ‘Yes’ to reopen the WO Purchase Requisition Lines. We need to reopen the WO Requisition so we can remove the Part Line and Remove the Material Line as it is still showing as required.

 

Is this possible? Is there another way to delete the Material Line?


2 replies

Userlevel 4
Badge +11

Has anyone come across this? It is starting to cause more problems.

Userlevel 3
Badge +4

It is not possible to delete the material line if you haven’t selected YES option to reopen the Purchase Requisition line when cancelling the purchase order line. You would encounter the error “The Maint Material Requisition is used by 1 rows in another object (Maint Material Req Line).” if you try to delete the material order line in such a scenario.

I think you can close the material line from the WO screen.
 

Reply