On work task line, you can see the current pre posting for cost center is set. if I changed the object ID, i would like the cost center in Pre Posting being changed automatically by a designated cost center value. my question would be, how to connect the cost center to object ID? Thank you.
Page 1 / 1
looking for the same functionality. have you found anything in here??
Hi @ronhu
Regarding “how to connect the cost center to object ID”, please check below steps.
Steps:
1. Open “Define Code String” page.
2. Here you can define Code parts where Logical code part Cost center. Multiple code parts can be defined with Logical code part = Cost center. However, only the 1st cost center in the hierarchy will be fetched to the object.