Hi,
It is possible to peg a started shop order with WIP to a DOP order created from a project supply request.
When doing so, the WIP is visible in the DOP cost as actual costs.
BUT
Those costs are not visible on the project.
I would expect that the WIP would be transferred to the project as used costs when the shop order is pegged to the DOP.
However, I imagine that because it is not possible to connect an activity to a shop order that is no longer planned, there is no mechanism for updating the M40 transactions with project details after they have already been created and used costs are not visible on the project until receiving the shop order.
Is this assumption correct or am I missing something?
Many thanks.