Hi,
Can someone tell me how I can change the currency rates for the part cost.
At this moment the part cost is calculated based on the current rate but I want to calculate it on a standard rate which is fixed for one year.
Thank you.
Hi,
Can someone tell me how I can change the currency rates for the part cost.
At this moment the part cost is calculated based on the current rate but I want to calculate it on a standard rate which is fixed for one year.
Thank you.
Best answer by Nick A
In that case it’s much simpler, because you are uing standard cost. All you need to do is copy cost set that holds the current standard cost (say for STD_2020), and then copy into a new cost set (say STD_2021), then export all the parts with their costs. Revalue those you need to, and then update the STD_2021 cost set with your new standards for the year. The calculation of parts and their currency rates should be done outside the application (e.g. Excel) and then update the parts in the new cost set.
This then gives you continual historical cost set references and analysis capabilities.
The above IS a manual process for revaluaing the standards for all parts, but once updated, you can then run the revaluation process to see the impact of the cost set change.