in the application for payment, user entered the header data and try to save ;

system raised the error message (the activity cost object doesn't exist)?

 

Best answer by Ieva Rituma

Hi,

 

This looks like a basic data setup issue. Please check the following basic data:

  1. The report codes used in the Sales Contract are valid,
  2. The report codes used in the sales contract don’t have the valid-to date in the past
  3. There is a valid cost/revenue element that applies to all items in the sales contract
  4. The dates on the project activity are not in the past

Hope this solves the error!

 

This topic has been closed for replies.

2 replies

Ieva Rituma
Superhero (Employee)
Forum|alt.badge.img+16
  • Superhero (Employee)
  • 429 replies
  • Answer
  • November 17, 2021

Hi,

 

This looks like a basic data setup issue. Please check the following basic data:

  1. The report codes used in the Sales Contract are valid,
  2. The report codes used in the sales contract don’t have the valid-to date in the past
  3. There is a valid cost/revenue element that applies to all items in the sales contract
  4. The dates on the project activity are not in the past

Hope this solves the error!

 


Forum|alt.badge.img+14
  • Author
  • Hero
  • 110 replies
  • November 18, 2021

system displayed this error ,

what shall i check ?