Skip to main content
Solved

application for payment (the activity cost object doesn't exist)

  • Nov 17, 2021 8:47 AM UTC
  • 2 replies
  • 332 views

Forum|alt.badge.img+14

Good Day;

in the application for payment, user entered the header data and try to save ;

system raised the error message (the activity cost object doesn't exist)?

 

Best answer by Ieva Rituma

Hi,

 

This looks like a basic data setup issue. Please check the following basic data:

  1. The report codes used in the Sales Contract are valid,
  2. The report codes used in the sales contract don’t have the valid-to date in the past
  3. There is a valid cost/revenue element that applies to all items in the sales contract
  4. The dates on the project activity are not in the past

Hope this solves the error!

 

View original
This topic has been closed for replies.

2 replies

Ieva Rituma
Superhero (Employee)
Forum|alt.badge.img+16
  • Superhero (Employee)
  • Answer
  • Nov 17, 2021 9:41 AM UTC

Hi,

 

This looks like a basic data setup issue. Please check the following basic data:

  1. The report codes used in the Sales Contract are valid,
  2. The report codes used in the sales contract don’t have the valid-to date in the past
  3. There is a valid cost/revenue element that applies to all items in the sales contract
  4. The dates on the project activity are not in the past

Hope this solves the error!

 


Forum|alt.badge.img+14

system displayed this error ,

what shall i check ?