HI,

In PSO i have added Resources shift for resources, after adding shift to resources , Resources are not getting visible in Resources Work space & Shift rota is also not getting displayed.

 

Is there any MPM need to create in FSM to get the Rota updated & getting displayed.

 

Regards,

Shiyaz

Hi @etmshiy ,

Exactly. When you have added a shift to a resource, you need to trigger a file containing source data & source data parameter entities to fetch the data to scheduling workspace from planning workspace.
 

You have the ability to set up a scheduled process in FSM to to fetch planning workspace data to Scheduling workspace. The triggering xml should be something similar to what I have attached. You may change the dataset id & rota id & execute it. You would see the rota details & resource details in Resource gannt.