PSO what is used for compare and Schedule assistance any one explian

  • Oct 28, 2022 9:22 AM UTC
  • 3 replies
  • 89 views

Forum|alt.badge.img+7

PSO what is used for compare and Schedule assistance any one explain 

3 replies

Forum|alt.badge.img+6
  • Hero (Employee)
  • Oct 28, 2022 1:35 PM UTC

Hi, 

The compare screen simply allows the user to quickly compare any number of activity or resource details next to one another. There are two dropdowns that have a multi select to choose what you wish to compare.

The assistance page helps the user to match activities to resources. By clicking on an activity in the top grid a list of resources which are suitable for that activity are display in a grid below. 

For a more detailed explanation of these pages though please review section 7 and 8 of the PSO Workbench User Guide.

Thanks,
Reece


Forum|alt.badge.img+7
  • Author
  • Do Gooder (Customer)
  • Oct 28, 2022 2:12 PM UTC

thanks for replying 

===================================

i have compare 2 resource  same skill and calendar available both are same location so PSO why schedule one engineer and not assigned task another Engineer any specific reason     


Forum|alt.badge.img+6
  • Hero (Employee)
  • Oct 28, 2022 2:38 PM UTC

 

It is hard to say without seeing your data. If you are on PSO version 6.10 then you can use the new explainability page, this page gives you a breakdown of why an activity has not been scheduled to a different resource or position in a shift. This might help with your questions. 

Hope this helps