Hi,

It is possible that PSO takes into account the stock of a resource before allocating the activity? Please take into account the fact that data comes from IFS Cloud, it is an integration between PSO and IFS Cloud (FSM). At the moment I do not see the ,,parts" tab on the resource, in PSO.

Thank you in advance!

Best Reagrds,

Miruna

Hi Miruna, parts are currently not supported by the IFS Cloud/PSO integration.


Hi @Alexander Heinze ,
do you know if this is currently in IFS roadmap?

Thank you


@Eleazar_AyaviriCarrillo , @Miruna M  I cannot give a precise answer, but for your planning: It’s not in the short-term roadmap, so don’t expect anything in the coming two releases.