Hi All,
Is there any option to mark National Holidays in PSO, so that system will not schedule the job for any resources.
I know we can add Holiday for individual resources, but can i block all the resources at one go.
Regards,
Shiyaz
Hi All,
Is there any option to mark National Holidays in PSO, so that system will not schedule the job for any resources.
I know we can add Holiday for individual resources, but can i block all the resources at one go.
Regards,
Shiyaz
On the Resource Planner you're able to add an unavailability for all resources on the dataset in one go.
Hi,
Thanks for the reply.. This solution iam aware, please refer the below link which i have shared solution to users. here the drawback is when ever i add new resources i need to add Holiday separately.
It must a general information you make once a year which will affect all resources no matter when they are added to Rota.
Regards,
Shiyaz
Hi Shiyaz,
This sounds like it could be useful for a number of people, but would probably need more thought to get the details right for some situations (like perhaps when a person transfers between countries).
Please feel free to raise it as an idea in the Community so that the product team can consider the option for future releases.
Thanks,
Carl