Hello everyone,
When I place an activity on another resource in the Gantt, a change is displayed but not executed. After a browser refresh, the activity is on the original resource.
If I make a change using the edit function, then it works. However, our customer would like to be able to change the activities in the Gantt directly.
The activities are sent via IFS Cloud.
Does anyone have any idea what the problem is?
Thank you for your help!