We are bulk importing work order/work task for the purpose of historical data. These are completed orders that client wishes to load into the system for reference purpose. Is there a way/process to auto set the status of these imported orders to “WORK DONE”?

 

Hey @Cpatel 

If you import the records, why not import with the desired status?

Cheers!


@Shneor Cheshin unable to do so. when adding the view 1 we dont get the OBJSTATE or STATE attribute. 2 when i tried to add the col manually, it did not update the status.


@Cpatel

What table are the records getting imported into?

Based on your answer  you  might be able to  use a simple business rule to update the field. 


@Morris  the table i am trying to update is the Jt_Task table for the cloud application. 

 