Is there a possibility for the user in the UI to fix a specific visit for a split activity for a specific time and possibly also to another source? Is it possible to fix this visit via the interface?

PSO Standalone.

 

Thanks for help!

Hi @Millsen ,

Yes. I think you should be able to do that. When the activity is split in PSO Resource gannt, click on it & in scheduling information tab on the right side of the screen, fix it to a dttm or to a resource.

Hope this helps. Cheers!

 


But, there is a pre-requisite here. The shifts of the resource that you are trying to assign the activity should also be splittable.Thanks!


Hi @Charith Fernando !

That’s exactly what we’ve tried and it fixed the whole activity (from the start) to the dttm.

Thanks for help! 