Hi All,
I have one resource that I can’t add to a region.
His ID will not show up in the drop down in Scheduling Resource Regions screen.
Any clue why he’s being filtered out?
Thanks,
Rob
Hi All,
I have one resource that I can’t add to a region.
His ID will not show up in the drop down in Scheduling Resource Regions screen.
Any clue why he’s being filtered out?
Thanks,
Rob
Yes it was.
In the end, we had to manually remove him entirely from the system and put him back in from the start (new user).
It was like he was being filtered out of the list of available resources.
Thanks for your help. Truly appreciate it.
Rob
they do
Ok, one last idea. In the Resource Detail screen, in tab “Employee” for TMCCOY, can you check if the “Primary Scheduling” flag is set to “No”?
It should be set to Yes, to use as a scheduling resource.
Yes, the company is correct
Here are two entries from Resources:
The top one appears as a possible selection, the bottom one doesn’t
Ok, so both of them have an employee record? If you check the employees section on the company screen you should be able to see that quickly.
Yes, the company is correct
Here are two entries from Resources:
The top one appears as a possible selection, the bottom one doesn’t
Are you checking in the correct company? In the upper right hand corner you have a selector. If it’s the one you expect, is the resource connected to it?
Enter your username or e-mail address. We'll send you an e-mail with instructions to reset your password.