Why when we connect a PO to an activity project the cost changes?

  • January 5, 2023
  • 1 reply
  • 62 views

Forum|alt.badge.img+1

Hi,

when I connect a PO manually to an activity project, the “Net Amount/Base” is changed in automatic to a different amount. What’s the logic behind it? Why and how it is changed?

 

Connect a PO manually to an activity project -  I mean that on PO view, I right-click on the PO line >  Project Connection > Connect to Activity > select the appropriate activity > ok

 

Thank you

Paola

1 reply

Forum|alt.badge.img+12
  • Hero (Partner)
  • January 12, 2023

Hi,

My guess is that you have a project specific supplier agreement with a line for the part you are purchasing.

When the PO line is not project connected, it must be fetching standard price. However, as soon as you connect the PO line to a project activity, if there was a supplier agreement for the project, where a different price for part is agreed, you will have this price in the purchase order line.

AGREEMENT

Hope this helps

Asanka