We start the process by creating a request for a product from the purchasing material request screen. We have an approval process set up for requests. Once the request is approved, purchasing personnel can change the material supplier or even split the request into two different suppliers. However, this operation cannot be performed because it is approved. How can we proceed without putting it through the approval process again?

@karacamelihcan did you check if you have the Allow Changes after Authorization checkbox checked in the PR Authorization Rule?