Hi,

Due to summer holiday in the company, we have created the Schedule Exception with “day type” weekend for the period of time( two weeks ) in July 2020, as an example see  below for the 13-07-2020.

However, we will still like to be able to create PO’s and recieve PO’s. Since our department for goods recieve is not closed. Does anybody have experience with that scenario ? What to do ?

Best Regards,

Marianne

I found out, you can choose between Distribution Calendar and Manufacturing Calendar at the Enterprise Site page.

I ended up making a new Calendar ( without exceptions) for the Distribution - so they still can ship goods and make goods recieve.

 