Team, please assist & point us in the right direction to resolve the following. We are on Apps9
When Registering PO Arrivals on PO 8737, the user received an error stating: Connecting a Purchase Order to a project is only allowed when the Purchase Order is in Planned Status.
The Order of Operations for our order is:
- Customer Order created with a connected Project
- Customer Order Released - which created Purchase Order with linked project in Planned status
- Purchase Order Released - sent to Supplier. Supplier sent parts to our warehouse
- Team trying to receive in the parts, and is receiving the following error:
Confirmed there were no changes on the line items for the customer order, purchase order or the project activities.
Please help determine why we are receiving this message on this Purchase Order.
Thanks